Construction progress
Two slabs cast, third slab formwork erected
Last updated October 16, 2026
Overall progress: 20%. Approximate engineering estimate.
| 20%
Two slabs cast, third slab formwork erected

Front view from the access road, with neighbouring buildings 
Street-front view of the concrete frame: two cast slabs with formwork for the next slab on top 
Frame seen from the street, left corner with neighbouring skeletons 
Full frontal view, two cast slabs and formwork on top 
Front bays: curved slab edge, column grid and third-slab formwork above 
Close view of ground and first-floor columns and the curved slab edge
| 16%
Timber decking and column starter bars on the deck, neighbours visible
low confidence on which deck this is
View from the formwork deck: timber decking, column starter bars and the access road
| 15%
Slab reinforcement complete, concrete pump on site, pour
walkaround-03 shows one cast slab with column forms/shuttering above, pump boom nearby
Concrete pump set up beside the building; slab reinforcement mat and curved edge formwork Walk-around of the frame from ground level: columns, one cast slab, formwork above